Factory Structure Dismantling in Thailand

Most dismantling contractors quote you a price to take a factory down. We usually quote you a payment.

20+ years in the machinery trade
Free site survey
Net position quoted upfront
Projects across Thailand

Inside a factory being cleared

Three different things, priced three different ways.

MachineryResale value as working equipment
Value
Structural steelMaterial value, as reusable sections or scrap
Value
Everything elseLabour, disposal, permits and reinstatement
Cost

We quote you the net of the two.

The reason is simple arithmetic. A factory being cleared contains three different things:

  • Machinery with real resale value
  • Structural steel with material value
  • Everything else, which is a cost

A demolition contractor usually prices the whole job as a cost, and machinery that goes out with the structure is often valued by weight, as scrap. That is how plants lose recoverable value on the way to a cleared site.

We start from the assets. We value the machinery as machinery and the steel as steel, then set the cost of the work against what it all recovers.

On most projects we take on, the recovery is higher than the cost. The site ends up net positive, and we pay you rather than invoice you.

This is not true of every project. A plant with only a bare shell and end-of-life equipment is a cost, and we’ll tell you that before you commit.

If you have serviceable machinery still standing, find out which side of the line you’re on before you accept a demolition quotation.

Sheet metal processing line inside a factory hall

How we work

We do not keep our own demolition crews or engineers. We subcontract, and choose the right specialist for each part of the job.

A press line, a chemical plant, a steel portal frame and an asbestos roof are four different disciplines. One general crew does at most one of them well.

What we bring

  • Asset knowledge
  • Buyer network
  • Project coordination
  • One point of accountability

What the subcontractor brings

  • The licence
  • The registered engineer
  • The equipment for that specific scope
Engineers inspecting industrial equipment on a factory floor

The practical difference to you: a demolition contractor is optimising the cost of knocking the building down. We’re optimising the net position, because that’s where our interest and yours are the same.

What factory structure dismantling covers

Machinery

Machinery dismantling and removal

Disconnection, decommissioning, breakdown and removal. For resale or relocation, it is taken apart so it can go back together. Otherwise it goes for disposal.

Steel

Structural steel

Portal frames, pre-engineered steel buildings, roof trusses and purlins, metal sheet cladding, mezzanines, gantries, racking, platforms, silos, tanks and pipe racks.

How the frame is cut decides whether it sells as reusable sections or as scrap. The price difference is significant.

Building

Building dismantling and concrete demolition

Walls, slabs, foundations, roofing and cladding, to bare shells or to bare land.

Services

Services strip-out

Electrical distribution, cabling, switchgear, compressed air, process piping, HVAC, extraction and fire systems.

Handover

Site clearance and handover

Debris removal, waste segregation, licensed disposal, and the site left in the condition your lease or sale contract requires.

The factory structure dismantling process

1

Phase 1: Survey, asset inventory and hazardous materials

We survey the structure, list everything with resale value and check for hazardous materials. You get a method statement covering sequence, equipment, crew and controls.

2

Phase 2: Preparation

We secure and hoard the site, set exclusion zones, and disconnect utilities and certify them dead. We clear remaining contents, brief the crew and notify neighbouring tenants inside industrial estates.

3
The decision that sets the money

Phase 3: Assets out first

Machinery and anything with resale value comes out intact before structural work starts. Once demolition begins, a machine that could have been sold becomes scrap.

4

Phase 4: Structural and building dismantling

Top down, in reverse of construction order: roof and cladding, structural steel, walls and partitions, then slabs and foundations if in scope. Materials are sorted as they come out: reusable steel, recyclable metals, concrete for crushing and general waste.

5

Phase 5: Clearance, disposal and handover

We clear the site, remove waste through licensed facilities with documentation, make the ground safe and formally hand it over.

Press brake machine inside an older factory hall with a steel roof truss

Machinery comes out intact before the structure comes down.

Two checks that decide the outcome

  • Asset inventory: we establish what is worth money before anything is treated as scrap, and before a single thing is cut.
  • Hazardous materials survey: older Thai industrial buildings may contain asbestos, most often in asbestos-cement roofing sheets, older insulation and gaskets. Finding it after work starts stops the job.

On projects involving asbestos, dangerous chemicals or contaminated ground, we arrange full environmental reporting before and after the work through our specialist partners.

How the net position works

Value recovered

  • Machinery: sold as working equipment wherever a buyer exists, directly, on consignment or through auction. Intact, properly marketed machinery is usually worth considerably more than its scrap weight.
  • Structural steel: reusable steel is worth more than scrap. The cutting method decides which you get.
  • Non-ferrous metals and cabling: copper, aluminium and stainless carry material value well above general scrap.

Cost of the work

  • Labour, equipment, disposal, permits and the site reinstatement your contract requires

We quote you the net of those two numbers.

On most projects with serviceable machinery still in place, the net runs in your favour and we pay you. If the site is mostly structure and end-of-life equipment, it runs the other way, and we’ll tell you at survey stage.

You should know the number before you commission demolition, not after. Once the building is coming down, the machinery question has already been answered for you, badly.

Three ways to sell the machinery

The machinery itself can be sold three ways. Which one fits depends on your deadline and on how much time the machines get in the market.

RouteHow it worksFits when
Sold directly to a buyerFastest, with the price agreed before the machine leaves.You have a fixed date to hand the site back.
On consignmentSlowest, because the machine is marketed until a buyer is found.You have time, and the machine is in good condition.
Through auctionA fixed sale date, with the price set by competing bids.There are many items, or the market price is hard to judge.

Permits and who is responsible for what

Under the Building Control Act B.E. 2522, demolishing some buildings needs permission from the local authority. This depends mainly on the building’s height and how close it stands to other buildings or a public place.

A licensed factory also has separate obligations to the Department of Industrial Works (DIW) under the Factory Act.

Where permission is needed, there are two routes:

  • Permit: the local authority has 45 days to decide and can extend that period twice.
  • Notification: work can start once the authority issues its receipt.

The local authority confirms which route applies to your building, so allow for it before the start date.

Both routes need the professionals responsible for the work to be named, including the supervisor. Your local authority confirms the exact documents it needs.

We assist with the applications, but they are made in the site owner’s name, not ours. We:

  • Prepare what’s needed
  • Work with the subcontractor’s engineer on drawings and calculations
  • Keep the paperwork moving, because permits, not the work, are what delay these projects

If the plant is a licensed factory being closed, the DIW obligations run in parallel. See our factory closure page.

How long it takes

It depends on scope. These are the typical ranges:

ScopeTypical duration
Machinery only (clearance of plant and equipment)around 2 months
Full clearance including the buildingaround 6 months
Range across all project sizes2 to 12 months

These ranges come from our own projects. What changes the timeline:

  • Size
  • Access
  • How much of the site is taken down
  • Hazardous materials
  • Marketing time for the machinery, which is the one you control most

Where we do factory structure dismantling in Thailand

Nationwide. Most projects are in the EEC (Chonburi, Rayong, Chachoengsao), Bangkok and Samut Prakan, and Ayutthaya and Pathum Thani.

This includes work inside industrial estates, where access, noise, working hours and neighbouring tenants all limit what can be done.

Container port with cranes on the Eastern Seaboard

EEC

Chonburi, Rayong, Chachoengsao

Wat Arun on the Chao Phraya River, Bangkok

Bangkok and Samut Prakan

Wat Chaiwatthanaram in Ayutthaya

Ayutthaya and Pathum Thani

Frequently asked questions

How much does factory dismantling cost?

+

Often nothing. On most projects with serviceable machinery still in place, the recovered value exceeds the cost of the work and we pay you. Where it doesn’t, the cost depends on structure type and size, scope, access, hazardous materials, haulage distance and the reinstatement condition required. We survey and quote the net position either way, and the survey is free.

Do I need a permit to dismantle a factory building?

+

It depends on the building. Under the Building Control Act B.E. 2522, demolishing some buildings needs a permit or a notification to the local authority, depending mainly on height and how close the building is to others or to a public place. A licensed factory also has separate DIW obligations under the Factory Act. We assist with the applications, which are made in the site owner’s name.

How long does it take?

+

Machinery-only clearance is around 2 months. A full clearance including the building is around 6 months. Across all sizes the range is 2 to 12 months.

What happens to the machinery inside?

+

It comes out first, intact, and is valued and sold as working equipment wherever a buyer exists. This is why the conversation should happen before you book a demolition contractor, not after.

What if there’s asbestos?

+

Older Thai industrial buildings may contain asbestos, most often in asbestos-cement roofing sheets. We survey for it, and on projects involving asbestos or other contaminants we arrange full environmental reporting before and after the work through specialist partners. Disposal goes through licensed facilities with the documentation handed to you. For licensed factories this matters: a Ministry of Industry notification in force since 1 November 2023 makes the factory, as waste generator, responsible for its waste until it is fully disposed of.

Find out whether your site is a cost or a payment

We survey, inventory what’s recoverable, and quote you the net position. The survey is free and there’s no obligation.